Combined Cycle Power Plant Baseline Schedule
Table of Contents
Combined Cycle Power Plant Baseline Schedule
Executive Summary
This document presents a comprehensive baseline schedule for a Combined Cycle Power Plant (CCPP) project, covering all phases from initial development through engineering, procurement, construction, and testing to commercial operation. The schedule has been developed based on industry best practices and provides a detailed roadmap for project execution.
The baseline schedule encompasses a total project duration of 42 months (3.5 years) from Notice to Proceed (NTP) to Commercial Operation Date (COD). Each project phase has been broken down into detailed activities with durations, logical relationships, resource requirements, and deliverables.
This schedule serves as the foundation for project planning, monitoring, and control throughout the CCPP project lifecycle. It identifies critical path activities, key milestones, and potential risk areas, providing a robust framework for successful project execution.
Table of Contents
- Introduction
- Project Overview
- Master Project Schedule
- Engineering Phase Schedule
- Procurement Phase Schedule
- Construction Phase Schedule
- Testing and Commissioning Schedule
- Schedule Validation
- Schedule Management Plan
- Appendices
Introduction
Purpose and Scope
This baseline schedule document provides a comprehensive timeline for the planning, engineering, procurement, construction, and commissioning of a Combined Cycle Power Plant. It serves as the primary planning and control tool for project execution and will be used to:
- Establish the project timeline and key milestones
- Identify and manage the critical path
- Allocate resources effectively
- Monitor and control project progress
- Identify and mitigate schedule risks
- Communicate project status to stakeholders
Methodology
The schedule was developed using a bottom-up approach, with detailed schedules created for each project phase and then integrated into a master schedule. Industry benchmarks and best practices were incorporated to ensure realistic durations and logical relationships. The schedule was validated through a comprehensive review process to ensure completeness, logical consistency, and resource feasibility.
Schedule Structure
The schedule is structured according to the following Work Breakdown Structure (WBS):
- Project Development
- Engineering
- Process Engineering
- Mechanical Engineering
- Civil/Structural Engineering
- Electrical Engineering
- Instrumentation and Control Engineering
- Other Engineering Disciplines
- Procurement
- Major Equipment
- Balance of Plant Equipment
- Construction Subcontracts
- Construction
- Site Preparation
- Civil Works
- Mechanical Installation
- Electrical Installation
- Instrumentation Installation
- Testing and Commissioning
- Pre-commissioning
- Commissioning
- Performance Testing
- Handover
Project Overview
Project Description
The Combined Cycle Power Plant consists of gas turbines, heat recovery steam generators (HRSGs), and a steam turbine to generate electricity efficiently by utilizing both gas and steam cycles. The plant includes all necessary balance of plant systems, electrical systems, control systems, and auxiliary facilities required for operation.
Key Project Parameters
Parameter | Value |
---|---|
Plant Capacity | Approximately 500-800 MW |
Configuration | 2x1 or 1x1 Combined Cycle |
Major Components | Gas Turbines, HRSGs, Steam Turbine, Generators |
Project Duration | 42 months (NTP to COD) |
Major Phases | Development, Engineering, Procurement, Construction, Commissioning |
Project Organization
The project will be executed by an integrated team comprising:
- Owner's team
- Engineering, Procurement, and Construction (EPC) contractor
- Major equipment vendors
- Specialized subcontractors
- Commissioning specialists
Master Project Schedule
The master schedule integrates all project phases and provides an overall timeline from Notice to Proceed to Commercial Operation. It identifies key milestones, phase overlaps, and the critical path through the entire project.
Project Timeline Summary
Phase | Start (Month) | Finish (Month) | Duration (Months) | Overlap with Other Phases |
---|---|---|---|---|
Project Development | 0 | 12 | 12 | Engineering (2 months) |
Engineering | 10 | 26 | 16 | Project Development (2 months), Procurement (10 months) |
Procurement | 16 | 36 | 20 | Engineering (10 months), Construction (8 months) |
Construction | 28 | 38 | 10 | Procurement (8 months), Testing & Commissioning (2 months) |
Testing & Commissioning | 36 | 42 | 6 | Construction (2 months) |
Key Project Milestones
Milestone ID | Description | Schedule Date (Month) |
---|---|---|
MS1 | Project Sanction / Notice to Proceed | Month 0 |
MS2 | Environmental Permits Secured | Month 9 |
MS3 | Engineering Kickoff | Month 10 |
MS4 | Process Design Basis Approved | Month 12 |
MS5 | 30% Engineering Complete | Month 16 |
MS6 | Major Equipment Purchase Orders Placed | Month 20 |
MS7 | 60% Engineering Complete | Month 21 |
MS8 | 90% Engineering Complete | Month 24 |
MS9 | Engineering IFC Package Complete | Month 26 |
MS10 | Site Mobilization | Month 28 |
MS11 | Major Foundations Complete | Month 32 |
MS12 | Gas Turbine Delivery | Month 33 |
MS13 | Steam Turbine Delivery | Month 34 |
MS14 | HRSG Delivery Complete | Month 32 |
MS15 | Gas Turbine Set on Foundation | Month 34 |
MS16 | Steam Turbine Set on Foundation | Month 34 |
MS17 | Mechanical Completion | Month 38 |
MS18 | Commissioning Start | Month 36 |
MS19 | First Fire of Gas Turbine | Month 38 |
MS20 | Steam Turbine Synchronized to Grid | Month 39 |
MS21 | Combined Cycle Integration Complete | Month 40 |
MS22 | Performance Testing Complete | Month 41 |
MS23 | Commercial Operation Date (COD) | Month 42 |
Critical Path
The critical path for the project runs through:
- Environmental permitting
- Gas turbine procurement
- Gas turbine foundation construction
- Gas turbine installation
- Gas turbine commissioning
- Combined cycle integration
- Performance testing
Engineering Phase Schedule
The Engineering Phase spans from Month 10 to Month 26 (16 months) and includes all design activities from conceptual design through detailed engineering to issued-for-construction documentation.
Engineering Activities Summary
Activity Category | Start (Month) | Finish (Month) | Key Deliverables |
---|---|---|---|
Project Kickoff and Mobilization | 10 | 11 | Project Execution Plan, Engineering Management Plan |
Process Design | 11 | 14 | Process Design Basis, Heat & Mass Balance, PFDs, P&IDs |
Equipment Sizing and Specifications | 13 | 15 | Equipment Data Sheets, Specifications |
Conceptual Design | 14 | 16 | Conceptual Drawings, 30% Design Package |
Detailed Design - Civil/Structural | 16 | 20 | Foundation Drawings, Structural Steel Drawings |
Detailed Design - Mechanical | 16 | 21 | Mechanical Drawings, Equipment Layouts |
Detailed Design - Electrical | 16 | 21 | Electrical Drawings, Cable Schedules |
Detailed Design - I&C | 16 | 21 | Instrument Index, Loop Diagrams, Control System Design |
Design Reviews and Optimization | 21 | 23 | 60% Design Package, Review Comments |
Final Design and Documentation | 23 | 26 | 90% Design Package, IFC Drawing Package |
Engineering Milestones
Milestone ID | Description | Schedule Date (Month) |
---|---|---|
EM1 | Project Kickoff Meeting | Month 10 |
EM2 | Process Design Basis Approval | Month 12 |
EM3 | 30% Design Review Completion | Month 16 |
EM4 | 60% Design Review Completion | Month 21 |
EM5 | 90% Design Review Completion | Month 24 |
EM6 | Issued for Construction (IFC) Package Release | Month 26 |
Procurement Phase Schedule
The Procurement Phase spans from Month 16 to Month 36 (20 months) and includes vendor selection, contract negotiation, manufacturing, factory testing, and delivery of all equipment and materials.
Procurement Activities Summary
Activity Category | Start (Month) | Finish (Month) | Key Deliverables |
---|---|---|---|
Procurement Strategy Development | 16 | 17 | Procurement Strategy Document |
Vendor Prequalification | 17 | 19 | Approved Vendor List |
Gas Turbine Procurement | 17 | 33 | Gas Turbine Delivery |
Steam Turbine Procurement | 18 | 34 | Steam Turbine Delivery |
HRSG Procurement | 18 | 32 | HRSG Delivery |
Generator Procurement | 19 | 32 | Generator Delivery |
Control System Procurement | 20 | 32 | Control System Delivery |
Electrical Equipment Procurement | 21 | 33 | Electrical Equipment Delivery |
Balance of Plant Equipment Procurement | 22 | 34 | BOP Equipment Delivery |
Construction Subcontractor Selection | 24 | 28 | Signed Subcontracts |
Long-Lead Items
Equipment | Procurement Duration (Months) | Manufacturing Duration (Months) | Delivery Date (Month) |
---|---|---|---|
Gas Turbine | 16 | 13 | Month 33 |
Steam Turbine | 16 | 12 | Month 34 |
HRSG | 14 | 11 | Month 32 |
Generator | 13 | 10 | Month 32 |
Main Transformer | 12 | 9 | Month 33 |
Control System | 12 | 9 | Month 32 |
Construction Phase Schedule
The Construction Phase spans from Month 28 to Month 38 (10 months) and includes all site activities from mobilization through civil works, mechanical and electrical installation, to mechanical completion.
Construction Activities Summary
Activity Category | Start (Month) | Finish (Month) | Key Deliverables |
---|---|---|---|
Construction Mobilization | 28 | 29 | Site Establishment |
Site Preparation | 29 | 31 | Graded Site, Access Roads, Drainage |
Foundations and Civil Works | 30 | 34 | Foundations, Buildings |
Major Equipment Installation | 33 | 35 | Installed Major Equipment |
Piping Installation | 34 | 36 | Installed Piping Systems |
Electrical Installation | 34 | 36 | Installed Electrical Systems |
Instrumentation Installation | 35 | 37 | Installed Instruments |
Mechanical Completion | 37 | 38 | Mechanical Completion Documentation |
Construction Milestones
Milestone ID | Description | Schedule Date (Month) |
---|---|---|
CM1 | Construction Mobilization Complete | Month 29 |
CM2 | Site Preparation Complete | Month 31 |
CM3 | Major Foundations Complete | Month 32 |
CM4 | Buildings Enclosed | Month 34 |
CM5 | Gas Turbine Set on Foundation | Month 34 |
CM6 | Steam Turbine Set on Foundation | Month 34 |
CM7 | HRSG Erection Complete | Month 35 |
CM8 | Main Piping Systems Complete | Month 36 |
CM9 | Electrical Systems Complete | Month 36 |
CM10 | Control Systems Complete | Month 37 |
CM11 | Mechanical Completion of All Systems | Month 38 |
Testing and Commissioning Schedule
The Testing and Commissioning Phase spans from Month 36 to Month 42 (6 months) and includes all activities from pre-commissioning through commissioning, performance testing, to commercial operation.
Testing and Commissioning Activities Summary
Activity Category | Start (Month) | Finish (Month) | Key Deliverables |
---|---|---|---|
Commissioning Team Mobilization | 36 | 37 | Commissioning Plan, Procedures |
Auxiliary Systems Pre-commissioning | 37 | 38 | Pre-commissioning Reports |
Gas Turbine Commissioning | 38 | 39 | GT Commissioning Report |
HRSG Commissioning | 38 | 39 | HRSG Commissioning Report |
Steam Turbine Commissioning | 39 | 40 | ST Commissioning Report |
Combined Cycle Integration | 40 | 40 | Integration Report |
Reliability Testing | 40 | 41 | Reliability Run Reports |
Performance Testing | 41 | 41 | Performance Test Reports |
Handover and Commercial Operation | 41 | 42 | Commercial Operation Certificate |
Testing and Commissioning Milestones
Milestone ID | Description | Schedule Date (Month) |
---|---|---|
TM1 | Commissioning Team Mobilized | Month 37 |
TM2 | Auxiliary Systems Pre-commissioning Complete | Month 38 |
TM3 | Gas Turbine First Fire | Month 39 |
TM4 | Steam Turbine Synchronized to Grid | Month 39 |
TM5 | Combined Cycle Integration Complete | Month 40 |
TM6 | 72-Hour Reliability Run Complete | Month 41 |
TM7 | Performance Testing Complete | Month 41 |
TM8 | Commercial Operation Date | Month 42 |
Schedule Validation
A comprehensive validation of the baseline schedule has been performed to ensure completeness, logical consistency, and resource feasibility. The validation confirmed that:
- All project phases and components are adequately covered
- Logical relationships between activities are appropriate
- The critical path is valid and continuous
- Resource allocations are reasonable and achievable
- Contingencies are appropriate for identified risks
The schedule validation identified some areas for potential enhancement, which have been incorporated into the final baseline schedule:
- Enhanced interface management between engineering and procurement
- More detailed resource histograms for the construction phase
- Refined contingency allocations based on risk assessment
Schedule Management Plan
Schedule Updates and Reporting
- Weekly progress updates during construction and commissioning
- Bi-weekly updates during engineering and procurement
- Monthly executive reporting throughout project
- Formal schedule revisions quarterly or upon major changes
Change Management Process
- All schedule changes must follow the formal change control process
- Impact analysis required for all schedule changes
- Approval levels based on magnitude of schedule impact:
- < 1 week: Project Manager approval
- 1-4 weeks: Project Director approval
-
4 weeks: Executive Committee approval
Performance Measurement
- Earned Value Management (EVM) will be used to track schedule performance
- Schedule Performance Index (SPI) will be calculated monthly
- Variance thresholds:
- SPI 0.95-1.05: Acceptable
- SPI 0.90-0.95 or 1.05-1.10: Requires monitoring
- SPI < 0.90 or > 1.10: Requires corrective action
Recovery Planning
- Recovery plans will be developed when:
- Critical path activities are delayed by more than 5 working days
- SPI falls below 0.90 for two consecutive reporting periods
- Key milestones are forecasted to be delayed
Appendices
Detailed Phase Schedules
- Engineering Phase Detailed Schedule
- Procurement Phase Detailed Schedule
- Construction Phase Detailed Schedule
- Testing and Commissioning Detailed Schedule
Resource Histograms
- Engineering Resources
- Procurement Resources
- Construction Resources
- Commissioning Resources
Schedule Risk Analysis
- Risk Register
- Schedule Contingency Analysis
- Probabilistic Schedule Analysis
Reference Documents
- Industry Benchmarks
- Historical Project Data
- Scheduling Standards and Guidelines
This baseline schedule provides a comprehensive framework for the planning, execution, and control of the Combined Cycle Power Plant project. It will be maintained and updated throughout the project lifecycle to reflect actual progress and changes in project scope or conditions.