Combined Cycle Power Plant Baseline Schedule

Combined Cycle Power Plant Baseline Schedule

Executive Summary

This document presents a comprehensive baseline schedule for a Combined Cycle Power Plant (CCPP) project, covering all phases from initial development through engineering, procurement, construction, and testing to commercial operation. The schedule has been developed based on industry best practices and provides a detailed roadmap for project execution.

The baseline schedule encompasses a total project duration of 42 months (3.5 years) from Notice to Proceed (NTP) to Commercial Operation Date (COD). Each project phase has been broken down into detailed activities with durations, logical relationships, resource requirements, and deliverables.

This schedule serves as the foundation for project planning, monitoring, and control throughout the CCPP project lifecycle. It identifies critical path activities, key milestones, and potential risk areas, providing a robust framework for successful project execution.

Table of Contents

  1. Introduction
  2. Project Overview
  3. Master Project Schedule
  4. Engineering Phase Schedule
  5. Procurement Phase Schedule
  6. Construction Phase Schedule
  7. Testing and Commissioning Schedule
  8. Schedule Validation
  9. Schedule Management Plan
  10. Appendices

Introduction

Purpose and Scope

This baseline schedule document provides a comprehensive timeline for the planning, engineering, procurement, construction, and commissioning of a Combined Cycle Power Plant. It serves as the primary planning and control tool for project execution and will be used to:

  • Establish the project timeline and key milestones
  • Identify and manage the critical path
  • Allocate resources effectively
  • Monitor and control project progress
  • Identify and mitigate schedule risks
  • Communicate project status to stakeholders

Methodology

The schedule was developed using a bottom-up approach, with detailed schedules created for each project phase and then integrated into a master schedule. Industry benchmarks and best practices were incorporated to ensure realistic durations and logical relationships. The schedule was validated through a comprehensive review process to ensure completeness, logical consistency, and resource feasibility.

Schedule Structure

The schedule is structured according to the following Work Breakdown Structure (WBS):

  1. Project Development
  2. Engineering
    • Process Engineering
    • Mechanical Engineering
    • Civil/Structural Engineering
    • Electrical Engineering
    • Instrumentation and Control Engineering
    • Other Engineering Disciplines
  3. Procurement
    • Major Equipment
    • Balance of Plant Equipment
    • Construction Subcontracts
  4. Construction
    • Site Preparation
    • Civil Works
    • Mechanical Installation
    • Electrical Installation
    • Instrumentation Installation
  5. Testing and Commissioning
    • Pre-commissioning
    • Commissioning
    • Performance Testing
    • Handover

Project Overview

Project Description

The Combined Cycle Power Plant consists of gas turbines, heat recovery steam generators (HRSGs), and a steam turbine to generate electricity efficiently by utilizing both gas and steam cycles. The plant includes all necessary balance of plant systems, electrical systems, control systems, and auxiliary facilities required for operation.

Key Project Parameters

ParameterValue
Plant CapacityApproximately 500-800 MW
Configuration2x1 or 1x1 Combined Cycle
Major ComponentsGas Turbines, HRSGs, Steam Turbine, Generators
Project Duration42 months (NTP to COD)
Major PhasesDevelopment, Engineering, Procurement, Construction, Commissioning

Project Organization

The project will be executed by an integrated team comprising:

  • Owner's team
  • Engineering, Procurement, and Construction (EPC) contractor
  • Major equipment vendors
  • Specialized subcontractors
  • Commissioning specialists

Master Project Schedule

The master schedule integrates all project phases and provides an overall timeline from Notice to Proceed to Commercial Operation. It identifies key milestones, phase overlaps, and the critical path through the entire project.

Project Timeline Summary

PhaseStart (Month)Finish (Month)Duration (Months)Overlap with Other Phases
Project Development01212Engineering (2 months)
Engineering102616Project Development (2 months), Procurement (10 months)
Procurement163620Engineering (10 months), Construction (8 months)
Construction283810Procurement (8 months), Testing & Commissioning (2 months)
Testing & Commissioning36426Construction (2 months)

Key Project Milestones

Milestone IDDescriptionSchedule Date (Month)
MS1Project Sanction / Notice to ProceedMonth 0
MS2Environmental Permits SecuredMonth 9
MS3Engineering KickoffMonth 10
MS4Process Design Basis ApprovedMonth 12
MS530% Engineering CompleteMonth 16
MS6Major Equipment Purchase Orders PlacedMonth 20
MS760% Engineering CompleteMonth 21
MS890% Engineering CompleteMonth 24
MS9Engineering IFC Package CompleteMonth 26
MS10Site MobilizationMonth 28
MS11Major Foundations CompleteMonth 32
MS12Gas Turbine DeliveryMonth 33
MS13Steam Turbine DeliveryMonth 34
MS14HRSG Delivery CompleteMonth 32
MS15Gas Turbine Set on FoundationMonth 34
MS16Steam Turbine Set on FoundationMonth 34
MS17Mechanical CompletionMonth 38
MS18Commissioning StartMonth 36
MS19First Fire of Gas TurbineMonth 38
MS20Steam Turbine Synchronized to GridMonth 39
MS21Combined Cycle Integration CompleteMonth 40
MS22Performance Testing CompleteMonth 41
MS23Commercial Operation Date (COD)Month 42

Critical Path

The critical path for the project runs through:

  1. Environmental permitting
  2. Gas turbine procurement
  3. Gas turbine foundation construction
  4. Gas turbine installation
  5. Gas turbine commissioning
  6. Combined cycle integration
  7. Performance testing

Engineering Phase Schedule

The Engineering Phase spans from Month 10 to Month 26 (16 months) and includes all design activities from conceptual design through detailed engineering to issued-for-construction documentation.

Engineering Activities Summary

Activity CategoryStart (Month)Finish (Month)Key Deliverables
Project Kickoff and Mobilization1011Project Execution Plan, Engineering Management Plan
Process Design1114Process Design Basis, Heat & Mass Balance, PFDs, P&IDs
Equipment Sizing and Specifications1315Equipment Data Sheets, Specifications
Conceptual Design1416Conceptual Drawings, 30% Design Package
Detailed Design - Civil/Structural1620Foundation Drawings, Structural Steel Drawings
Detailed Design - Mechanical1621Mechanical Drawings, Equipment Layouts
Detailed Design - Electrical1621Electrical Drawings, Cable Schedules
Detailed Design - I&C1621Instrument Index, Loop Diagrams, Control System Design
Design Reviews and Optimization212360% Design Package, Review Comments
Final Design and Documentation232690% Design Package, IFC Drawing Package

Engineering Milestones

Milestone IDDescriptionSchedule Date (Month)
EM1Project Kickoff MeetingMonth 10
EM2Process Design Basis ApprovalMonth 12
EM330% Design Review CompletionMonth 16
EM460% Design Review CompletionMonth 21
EM590% Design Review CompletionMonth 24
EM6Issued for Construction (IFC) Package ReleaseMonth 26

Procurement Phase Schedule

The Procurement Phase spans from Month 16 to Month 36 (20 months) and includes vendor selection, contract negotiation, manufacturing, factory testing, and delivery of all equipment and materials.

Procurement Activities Summary

Activity CategoryStart (Month)Finish (Month)Key Deliverables
Procurement Strategy Development1617Procurement Strategy Document
Vendor Prequalification1719Approved Vendor List
Gas Turbine Procurement1733Gas Turbine Delivery
Steam Turbine Procurement1834Steam Turbine Delivery
HRSG Procurement1832HRSG Delivery
Generator Procurement1932Generator Delivery
Control System Procurement2032Control System Delivery
Electrical Equipment Procurement2133Electrical Equipment Delivery
Balance of Plant Equipment Procurement2234BOP Equipment Delivery
Construction Subcontractor Selection2428Signed Subcontracts

Long-Lead Items

EquipmentProcurement Duration (Months)Manufacturing Duration (Months)Delivery Date (Month)
Gas Turbine1613Month 33
Steam Turbine1612Month 34
HRSG1411Month 32
Generator1310Month 32
Main Transformer129Month 33
Control System129Month 32

Construction Phase Schedule

The Construction Phase spans from Month 28 to Month 38 (10 months) and includes all site activities from mobilization through civil works, mechanical and electrical installation, to mechanical completion.

Construction Activities Summary

Activity CategoryStart (Month)Finish (Month)Key Deliverables
Construction Mobilization2829Site Establishment
Site Preparation2931Graded Site, Access Roads, Drainage
Foundations and Civil Works3034Foundations, Buildings
Major Equipment Installation3335Installed Major Equipment
Piping Installation3436Installed Piping Systems
Electrical Installation3436Installed Electrical Systems
Instrumentation Installation3537Installed Instruments
Mechanical Completion3738Mechanical Completion Documentation

Construction Milestones

Milestone IDDescriptionSchedule Date (Month)
CM1Construction Mobilization CompleteMonth 29
CM2Site Preparation CompleteMonth 31
CM3Major Foundations CompleteMonth 32
CM4Buildings EnclosedMonth 34
CM5Gas Turbine Set on FoundationMonth 34
CM6Steam Turbine Set on FoundationMonth 34
CM7HRSG Erection CompleteMonth 35
CM8Main Piping Systems CompleteMonth 36
CM9Electrical Systems CompleteMonth 36
CM10Control Systems CompleteMonth 37
CM11Mechanical Completion of All SystemsMonth 38

Testing and Commissioning Schedule

The Testing and Commissioning Phase spans from Month 36 to Month 42 (6 months) and includes all activities from pre-commissioning through commissioning, performance testing, to commercial operation.

Testing and Commissioning Activities Summary

Activity CategoryStart (Month)Finish (Month)Key Deliverables
Commissioning Team Mobilization3637Commissioning Plan, Procedures
Auxiliary Systems Pre-commissioning3738Pre-commissioning Reports
Gas Turbine Commissioning3839GT Commissioning Report
HRSG Commissioning3839HRSG Commissioning Report
Steam Turbine Commissioning3940ST Commissioning Report
Combined Cycle Integration4040Integration Report
Reliability Testing4041Reliability Run Reports
Performance Testing4141Performance Test Reports
Handover and Commercial Operation4142Commercial Operation Certificate

Testing and Commissioning Milestones

Milestone IDDescriptionSchedule Date (Month)
TM1Commissioning Team MobilizedMonth 37
TM2Auxiliary Systems Pre-commissioning CompleteMonth 38
TM3Gas Turbine First FireMonth 39
TM4Steam Turbine Synchronized to GridMonth 39
TM5Combined Cycle Integration CompleteMonth 40
TM672-Hour Reliability Run CompleteMonth 41
TM7Performance Testing CompleteMonth 41
TM8Commercial Operation DateMonth 42

Schedule Validation

A comprehensive validation of the baseline schedule has been performed to ensure completeness, logical consistency, and resource feasibility. The validation confirmed that:

  • All project phases and components are adequately covered
  • Logical relationships between activities are appropriate
  • The critical path is valid and continuous
  • Resource allocations are reasonable and achievable
  • Contingencies are appropriate for identified risks

The schedule validation identified some areas for potential enhancement, which have been incorporated into the final baseline schedule:

  1. Enhanced interface management between engineering and procurement
  2. More detailed resource histograms for the construction phase
  3. Refined contingency allocations based on risk assessment

Schedule Management Plan

Schedule Updates and Reporting

  • Weekly progress updates during construction and commissioning
  • Bi-weekly updates during engineering and procurement
  • Monthly executive reporting throughout project
  • Formal schedule revisions quarterly or upon major changes

Change Management Process

  • All schedule changes must follow the formal change control process
  • Impact analysis required for all schedule changes
  • Approval levels based on magnitude of schedule impact:
    • < 1 week: Project Manager approval
    • 1-4 weeks: Project Director approval
    • 4 weeks: Executive Committee approval

Performance Measurement

  • Earned Value Management (EVM) will be used to track schedule performance
  • Schedule Performance Index (SPI) will be calculated monthly
  • Variance thresholds:
    • SPI 0.95-1.05: Acceptable
    • SPI 0.90-0.95 or 1.05-1.10: Requires monitoring
    • SPI < 0.90 or > 1.10: Requires corrective action

Recovery Planning

  • Recovery plans will be developed when:
    • Critical path activities are delayed by more than 5 working days
    • SPI falls below 0.90 for two consecutive reporting periods
    • Key milestones are forecasted to be delayed

Appendices

Detailed Phase Schedules

  • Engineering Phase Detailed Schedule
  • Procurement Phase Detailed Schedule
  • Construction Phase Detailed Schedule
  • Testing and Commissioning Detailed Schedule

Resource Histograms

  • Engineering Resources
  • Procurement Resources
  • Construction Resources
  • Commissioning Resources

Schedule Risk Analysis

  • Risk Register
  • Schedule Contingency Analysis
  • Probabilistic Schedule Analysis

Reference Documents

  • Industry Benchmarks
  • Historical Project Data
  • Scheduling Standards and Guidelines

This baseline schedule provides a comprehensive framework for the planning, execution, and control of the Combined Cycle Power Plant project. It will be maintained and updated throughout the project lifecycle to reflect actual progress and changes in project scope or conditions.