Engineering Phase Schedule

Overview

The Engineering Phase is a critical foundation for the entire CCPP project. This phase typically spans 6-12 months depending on project complexity and size. The schedule below provides a detailed breakdown of engineering activities, milestones, and deliverables.

IDActivityDuration (weeks)PredecessorsResourcesDeliverables
E1Project Kickoff and Engineering Mobilization2-Project Manager, Engineering Manager, Discipline LeadsProject Execution Plan, Engineering Management Plan
E2Site Investigation and Data Collection4E1Civil Engineers, Geotechnical EngineersSite Investigation Report, Geotechnical Report
E3Process Design Basis Development3E1Process EngineersProcess Design Basis Document
E4Heat and Mass Balance Calculations3E3Process Engineers, Thermal EngineersHeat and Mass Balance Diagrams
E5Process Flow Diagrams (PFDs)4E4Process EngineersProcess Flow Diagrams
E6Piping and Instrumentation Diagrams (P&IDs)6E5Process Engineers, Instrumentation EngineersP&ID Drawings
E7Equipment Sizing and Specifications5E5Mechanical Engineers, Process EngineersEquipment Data Sheets, Specifications
E8Electrical Single Line Diagrams4E3Electrical EngineersElectrical Single Line Diagrams
E9Control System Architecture4E6Control Systems EngineersControl System Architecture Diagrams
E10Civil/Structural Conceptual Design4E2Civil/Structural EngineersConceptual Civil/Structural Drawings
E11Plant Layout Development5E7, E10All DisciplinesGeneral Arrangement Drawings
E1230% Design Review2E11All Disciplines, Project Manager30% Design Package, Review Comments
E13Civil/Structural Detailed Design8E12Civil/Structural EngineersFoundation Drawings, Structural Steel Drawings
E14Mechanical Detailed Design10E12Mechanical EngineersMechanical Drawings, Equipment Layouts
E15Piping Detailed Design12E14Piping EngineersPiping Isometric Drawings, Pipe Support Drawings
E16Electrical Detailed Design10E12Electrical EngineersElectrical Equipment Layouts, Cable Schedules
E17Instrumentation Detailed Design10E16Instrumentation EngineersInstrument Index, Loop Diagrams
E18Control Systems Detailed Design12E17Control Systems EngineersControl System Configuration, Logic Diagrams
E19HVAC Detailed Design8E14HVAC EngineersHVAC Drawings, Duct Layouts
E20Fire Protection Detailed Design8E14Fire Protection EngineersFire Protection Drawings
E2160% Design Review2E13, E14, E16, E17All Disciplines, Project Manager60% Design Package, Review Comments
E22Design Optimization and Refinement4E21All DisciplinesUpdated Design Documents
E23Procurement Specifications Finalization6E22All Disciplines, Procurement TeamFinal Procurement Specifications
E24Construction Drawings Development8E22All DisciplinesConstruction Drawings
E2590% Design Review2E23, E24All Disciplines, Project Manager90% Design Package, Review Comments
E26Design Finalization and Approval4E25All DisciplinesFinal Design Package
E27Issued for Construction (IFC) Documentation3E26Document Control, All DisciplinesIFC Drawing Package
E28Engineering Support for ProcurementOngoingE23All DisciplinesTechnical Bid Evaluations, Vendor Drawing Reviews
E29Engineering Support for ConstructionOngoingE27All DisciplinesRFI Responses, Field Change Notices
Milestone IDDescriptionSchedule Date (weeks from start)
EM1Project Kickoff MeetingWeek 1
EM2Process Design Basis ApprovalWeek 5
EM330% Design Review CompletionWeek 24
EM460% Design Review CompletionWeek 44
EM590% Design Review CompletionWeek 60
EM6Issued for Construction (IFC) Package ReleaseWeek 67
  1. Process Engineering

    • Heat and mass balance calculations
    • Process flow diagrams
    • Process data sheets
    • Performance specifications
  2. Mechanical Engineering

    • Equipment specifications and selection
    • Mechanical system design
    • HRSG design coordination
    • Turbine integration
  3. Civil/Structural Engineering

    • Foundation design
    • Structural steel design
    • Building design
    • Site development
  4. Electrical Engineering

    • Power distribution systems
    • Switchyard design
    • Generator interconnection
    • Lighting systems
  5. Instrumentation and Control Engineering

    • Control system architecture
    • Instrumentation selection
    • DCS/PLC programming specifications
    • SCADA systems
  6. Piping Engineering

    • Piping layouts
    • Pipe stress analysis
    • Pipe support design
    • Material specifications
  7. HVAC Engineering

    • Ventilation systems
    • Air conditioning systems
    • Equipment cooling
  8. Fire Protection Engineering

    • Fire detection systems
    • Fire suppression systems
    • Emergency response planning
  1. 30% Design Review

    • Confirm design basis and criteria
    • Validate major equipment selections
    • Review preliminary layouts
    • Identify potential design conflicts
  2. 60% Design Review

    • Detailed review of all discipline designs
    • Interference checking
    • Construction methodology review
    • Procurement package readiness
  3. 90% Design Review

    • Final design verification
    • Construction drawing completeness
    • Specification completeness
    • Regulatory compliance verification
  4. Final Design Approval

    • Complete design package verification
    • Client approval
    • Release for construction
  1. Interface with Procurement

    • Technical specifications for equipment
    • Vendor document review
    • Technical bid evaluations
    • Equipment delivery schedules
  2. Interface with Construction

    • Construction methodology input
    • Constructability reviews
    • Field change requests
    • As-built documentation
  3. Interface with Commissioning

    • System turnover packages
    • Commissioning procedures
    • Performance test protocols
    • Operating manuals and training materials
  4. Interface with Operations

    • Operability reviews
    • Maintenance accessibility
    • Spare parts recommendations
    • Training program development
  1. Design Verification

    • Independent checking of calculations
    • Peer reviews of drawings
    • 3D model reviews
    • Interference detection
  2. Standards Compliance

    • Industry code compliance checks
    • Regulatory requirement verification
    • Client standard adherence
    • Quality assurance audits
  3. Design Change Management

    • Formal change request process
    • Impact assessment procedures
    • Change approval workflow
    • Change implementation tracking

This engineering phase schedule provides a comprehensive framework for managing the design development of a combined cycle power plant, ensuring all technical aspects are properly addressed before proceeding to procurement and construction phases.