Testing and Commissioning Schedule
Table of Contents
Overview
The Testing and Commissioning Phase is the final technical phase before commercial operation of the CCPP. This phase typically spans 3-6 months and involves systematic testing of all plant systems, culminating in performance testing and handover.
| ID | Activity | Duration (weeks) | Predecessors | Resources | Deliverables |
|---|---|---|---|---|---|
| T1 | Commissioning Team Mobilization | 4 | C45 | Commissioning Manager, Team | Commissioning Plan |
| T2 | Commissioning Procedures Development | 6 | T1 | Commissioning Engineers | Commissioning Procedures |
| T3 | Commissioning Safety Plan Development | 3 | T1 | Safety Engineer, Commissioning Manager | Commissioning Safety Plan |
| T4 | Instrument Air System Pre-commissioning | 2 | C60 | Commissioning Team | System Pre-commissioning Report |
| T5 | Service Water System Pre-commissioning | 2 | C60 | Commissioning Team | System Pre-commissioning Report |
| T6 | Fire Protection System Pre-commissioning | 2 | C60 | Commissioning Team, Fire Protection Vendor | System Pre-commissioning Report |
| T7 | Electrical Distribution System Pre-commissioning | 3 | C60 | Electrical Commissioning Engineers | System Pre-commissioning Report |
| T8 | DC System Pre-commissioning | 2 | C60 | Electrical Commissioning Engineers | System Pre-commissioning Report |
| T9 | UPS System Pre-commissioning | 2 | C60 | Electrical Commissioning Engineers | System Pre-commissioning Report |
| T10 | Control System Pre-commissioning | 4 | C60, T7, T8, T9 | Control System Engineers, Vendor | System Pre-commissioning Report |
| T11 | Cooling Water System Pre-commissioning | 3 | C60, T5 | Mechanical Commissioning Engineers | System Pre-commissioning Report |
| T12 | Water Treatment System Pre-commissioning | 3 | C60, T5 | Mechanical Commissioning Engineers, Vendor | System Pre-commissioning Report |
| T13 | Fuel Gas System Pre-commissioning | 3 | C60, T4 | Mechanical Commissioning Engineers | System Pre-commissioning Report |
| T14 | HVAC System Pre-commissioning | 2 | C60, T4, T7 | Mechanical Commissioning Engineers | System Pre-commissioning Report |
| T15 | Auxiliary Systems Pre-commissioning | 4 | T4, T5, T7 | Commissioning Team | System Pre-commissioning Report |
| T16 | Gas Turbine Pre-commissioning | 4 | T10, T13, T15 | GT Vendor, Commissioning Team | GT Pre-commissioning Report |
| T17 | HRSG Pre-commissioning | 4 | T10, T11, T15 | HRSG Vendor, Commissioning Team | HRSG Pre-commissioning Report |
| T18 | Steam Turbine Pre-commissioning | 4 | T10, T11, T15 | ST Vendor, Commissioning Team | ST Pre-commissioning Report |
| T19 | Generator and Electrical Systems Pre-commissioning | 3 | T7, T16, T18 | Electrical Commissioning Engineers | Generator Pre-commissioning Report |
| T20 | DCS Final Check and Testing | 3 | T10, T16, T17, T18 | Control System Engineers, Vendor | DCS Testing Report |
| T21 | Electrical System Energization | 2 | T7, T19 | Electrical Commissioning Engineers | Energization Report |
| T22 | Chemical Cleaning of HRSG and Steam Systems | 3 | T17 | Commissioning Team, Specialty Contractor | Chemical Cleaning Report |
| T23 | Steam Blowing | 4 | T22 | Commissioning Team | Steam Blowing Report |
| T24 | Fuel Gas System Commissioning | 2 | T13 | Commissioning Team | System Commissioning Report |
| T25 | Gas Turbine First Fire | 1 | T16, T20, T24 | GT Vendor, Commissioning Team | First Fire Report |
| T26 | Gas Turbine Commissioning | 3 | T25 | GT Vendor, Commissioning Team | GT Commissioning Report |
| T27 | HRSG Commissioning | 3 | T17, T22, T23, T26 | HRSG Vendor, Commissioning Team | HRSG Commissioning Report |
| T28 | Steam Turbine Roll and Synchronization | 2 | T18, T27 | ST Vendor, Commissioning Team | ST Synchronization Report |
| T29 | Steam Turbine Commissioning | 3 | T28 | ST Vendor, Commissioning Team | ST Commissioning Report |
| T30 | Combined Cycle Integration | 2 | T26, T29 | Commissioning Team | Integration Report |
| T31 | Plant Control System Tuning | 3 | T30 | Control System Engineers, Vendor | Control System Tuning Report |
| T32 | Plant Reliability Run (24 hours) | 1 | T31 | Commissioning Team | Reliability Run Report |
| T33 | Plant Reliability Run (72 hours) | 1 | T32 | Commissioning Team | Reliability Run Report |
| T34 | Performance Test Preparation | 2 | T33 | Performance Test Engineer, Commissioning Team | Test Procedures |
| T35 | Gas Turbine Performance Testing | 1 | T34 | Performance Test Engineer, GT Vendor | GT Performance Test Report |
| T36 | Steam Turbine Performance Testing | 1 | T34 | Performance Test Engineer, ST Vendor | ST Performance Test Report |
| T37 | HRSG Performance Testing | 1 | T34 | Performance Test Engineer, HRSG Vendor | HRSG Performance Test Report |
| T38 | Combined Cycle Performance Testing | 2 | T35, T36, T37 | Performance Test Engineer, Commissioning Team | Plant Performance Test Report |
| T39 | Emissions Testing | 1 | T38 | Environmental Engineer, Third Party Tester | Emissions Test Report |
| T40 | Noise Testing | 1 | T38 | Environmental Engineer, Third Party Tester | Noise Test Report |
| T41 | Plant Trip and Recovery Testing | 1 | T38 | Commissioning Team | Trip and Recovery Test Report |
| T42 | Grid Code Compliance Testing | 2 | T38 | Electrical Commissioning Engineers, Grid Operator | Grid Compliance Report |
| T43 | Completion of Commissioning Punch List | 3 | T39, T40, T41, T42 | Commissioning Team | Resolved Punch List |
| T44 | Operations Training | 6 | T1 | Training Engineer, Operations Team | Training Completion Report |
| T45 | Operations Readiness Review | 2 | T44, T43 | Operations Manager, Commissioning Manager | Readiness Review Report |
| T46 | Preparation of Commissioning Documentation | 4 | T43 | Commissioning Engineers, Document Control | Commissioning Documentation |
| T47 | Provisional Acceptance Certificate | 1 | T45, T46 | Project Manager, Client | Provisional Acceptance Certificate |
| T48 | Handover to Operations | 2 | T47 | Commissioning Manager, Operations Manager | Handover Documentation |
| T49 | Commercial Operation | 0 | T48 | Project Manager, Operations Manager | Commercial Operation Certificate |
| Milestone ID | Description | Schedule Date (weeks from commissioning start) |
|---|---|---|
| TM1 | Commissioning Team Mobilized | Week 4 |
| TM2 | Commissioning Procedures Approved | Week 10 |
| TM3 | Auxiliary Systems Pre-commissioning Complete | Week 20 |
| TM4 | Gas Turbine First Fire | Week 28 |
| TM5 | Steam Turbine Synchronized to Grid | Week 36 |
| TM6 | Combined Cycle Integration Complete | Week 41 |
| TM7 | 72-Hour Reliability Run Complete | Week 45 |
| TM8 | Performance Testing Complete | Week 50 |
| TM9 | Commissioning Punch List Closed | Week 53 |
| TM10 | Provisional Acceptance Certificate Issued | Week 58 |
| TM11 | Commercial Operation Date | Week 60 |
Pre-commissioning activities involve checking individual components and systems before energization or introduction of process fluids:
-
Mechanical Systems
- Alignment checks
- Rotation checks
- Lubrication system checks
- Valve operation verification
- Strainer and filter installation verification
- Expansion joint inspection
-
Electrical Systems
- Insulation resistance testing
- Continuity testing
- Relay testing and calibration
- Transformer testing
- Switchgear testing
- Motor testing
-
Control Systems
- Loop checks
- Signal verification
- Instrument calibration
- Control logic verification
- HMI functionality testing
- Alarm system testing
-
Piping Systems
- Pressure testing completion verification
- Cleaning and flushing verification
- Support and hanger inspection
- Expansion provision verification
- Valve positioning verification
Commissioning activities involve energizing systems and introducing process fluids for functional testing:
-
Utility Systems
- Instrument air system
- Service water system
- Fire protection system
- HVAC system
- Electrical distribution system
-
Major Equipment
- Gas turbine commissioning
- HRSG commissioning
- Steam turbine commissioning
- Generator commissioning
- Water treatment system
-
Integrated Systems
- Combined cycle integration
- Plant control system tuning
- Load testing
- Reliability testing
- Performance optimization
Performance testing verifies that the plant meets contractual guarantees:
-
Test Parameters
- Power output
- Heat rate
- Emissions levels
- Start-up times
- Ramp rates
- Noise levels
-
Testing Methodology
- ASME PTC 46 (Overall Plant Performance)
- ASME PTC 22 (Gas Turbine Performance)
- ASME PTC 6 (Steam Turbine Performance)
- ASME PTC 4.4 (HRSG Performance)
- EPA Methods (Emissions Testing)
-
Test Conditions
- Base load operation
- Part load operation
- Ambient temperature correction
- Grid frequency variations
- Fuel composition variations
-
Acceptance Criteria
- Performance guarantees met
- Emissions compliance verified
- Reliability demonstrated
- Operations training completed
- Documentation delivered
- Punch list items resolved
-
Handover Documentation
- As-built drawings
- Operating manuals
- Maintenance manuals
- Test reports
- Commissioning records
- Warranty certificates
-
Regulatory Approvals
- Environmental compliance certification
- Electrical grid compliance certification
- Safety certification
- Operating permits
-
Commercial Handover
- Provisional acceptance certificate
- Performance security release
- Warranty period commencement
- Final payment milestone
- Commercial operation declaration
This testing and commissioning phase schedule provides a comprehensive framework for systematically testing and verifying all aspects of a combined cycle power plant, ensuring it meets performance guarantees and is ready for commercial operation.