Construction Phase Schedule
Table of Contents
Overview
The Construction Phase is where the physical plant takes shape. This phase typically spans 18-24 months and involves multiple disciplines working in coordination. The schedule below provides a detailed breakdown of construction activities, milestones, and critical path items.
ID | Activity | Duration (weeks) | Predecessors | Resources | Deliverables |
---|---|---|---|---|---|
C1 | Construction Mobilization | 4 | P79 | Construction Manager, Site Team | Site Establishment Report |
C2 | Site Clearing and Grading | 6 | C1 | Civil Subcontractor | Graded Site |
C3 | Site Access Roads and Drainage | 8 | C2 | Civil Subcontractor | Access Roads, Drainage System |
C4 | Temporary Facilities Installation | 6 | C2 | Construction Team | Temporary Facilities |
C5 | Piling Works | 10 | C3 | Civil Subcontractor | Completed Piling |
C6 | Underground Utilities Installation | 8 | C3 | Civil Subcontractor | Underground Utilities |
C7 | Gas Turbine Foundation | 12 | C5, P80(GT) | Civil Subcontractor | GT Foundations |
C8 | Steam Turbine Foundation | 10 | C5, P80(ST) | Civil Subcontractor | ST Foundations |
C9 | HRSG Foundation | 8 | C5, P80(HRSG) | Civil Subcontractor | HRSG Foundations |
C10 | Main Transformer Foundations | 6 | C5 | Civil Subcontractor | Transformer Foundations |
C11 | Control Building Foundation | 6 | C5 | Civil Subcontractor | Control Building Foundation |
C12 | Balance of Plant Foundations | 14 | C5, C6 | Civil Subcontractor | BOP Foundations |
C13 | Control Building Construction | 16 | C11 | Building Subcontractor | Control Building Structure |
C14 | Turbine Building Construction | 20 | C7, C8 | Building Subcontractor | Turbine Building Structure |
C15 | Water Treatment Building Construction | 14 | C12 | Building Subcontractor | Water Treatment Building |
C16 | Warehouse and Workshop Construction | 12 | C12 | Building Subcontractor | Warehouse and Workshop |
C17 | Cooling Tower Construction | 16 | C12 | Cooling Tower Subcontractor | Cooling Tower Structure |
C18 | Switchyard Construction | 16 | C10 | Electrical Subcontractor | Switchyard Structure |
C19 | Gas Turbine Delivery and Setting | 6 | C14, P12 | Mechanical Subcontractor, Vendor | Installed Gas Turbine |
C20 | Steam Turbine Delivery and Setting | 6 | C14, P22 | Mechanical Subcontractor, Vendor | Installed Steam Turbine |
C21 | HRSG Delivery and Erection | 12 | C9, P32 | Mechanical Subcontractor, Vendor | Erected HRSG |
C22 | Generator Installation | 6 | C19, C20, P42 | Mechanical Subcontractor, Vendor | Installed Generators |
C23 | Main Transformer Installation | 4 | C10, P62 | Electrical Subcontractor | Installed Transformers |
C24 | Fuel Gas System Installation | 10 | C12 | Mechanical Subcontractor | Fuel Gas System |
C25 | Cooling Water System Installation | 12 | C17 | Mechanical Subcontractor | Cooling Water System |
C26 | Water Treatment System Installation | 10 | C15, P72 | Mechanical Subcontractor | Water Treatment System |
C27 | Compressed Air System Installation | 8 | C16, P72 | Mechanical Subcontractor | Compressed Air System |
C28 | Fire Protection System Installation | 12 | C13, C14, C15, C16, P72 | Fire Protection Subcontractor | Fire Protection System |
C29 | HVAC System Installation | 10 | C13, C14, C15, C16, P72 | HVAC Subcontractor | HVAC System |
C30 | Main Piping Installation | 20 | C21, C24, C25, C26, C27 | Piping Subcontractor | Main Piping Systems |
C31 | Auxiliary Piping Installation | 16 | C30 | Piping Subcontractor | Auxiliary Piping Systems |
C32 | Pipe Insulation | 12 | C30, C31 | Insulation Subcontractor | Insulated Piping |
C33 | Main Cable Tray and Conduit Installation | 14 | C13, C14, C15, C16, C18 | Electrical Subcontractor | Cable Trays and Conduits |
C34 | Power Cable Installation | 12 | C33 | Electrical Subcontractor | Power Cables |
C35 | Control Cable Installation | 10 | C33 | Electrical Subcontractor | Control Cables |
C36 | Lighting System Installation | 8 | C33 | Electrical Subcontractor | Lighting System |
C37 | Grounding System Installation | 6 | C6 | Electrical Subcontractor | Grounding System |
C38 | Cathodic Protection System Installation | 6 | C6 | Electrical Subcontractor | Cathodic Protection System |
C39 | Instrument Installation | 12 | C30, C31, C33 | Instrumentation Subcontractor | Installed Instruments |
C40 | Control System Installation | 14 | C13, C34, C35, P52 | Control System Vendor | Installed Control System |
C41 | Electrical Equipment Installation | 12 | C34, P62 | Electrical Subcontractor | Installed Electrical Equipment |
C42 | Motor Control Center Installation | 8 | C34, P62 | Electrical Subcontractor | Installed MCCs |
C43 | UPS and DC System Installation | 6 | C13, C34, P62 | Electrical Subcontractor | Installed UPS and DC Systems |
C44 | Switchgear Installation | 8 | C13, C34, P62 | Electrical Subcontractor | Installed Switchgear |
C45 | Gas Turbine Mechanical Completion | 8 | C19, C24, C30, C39 | Mechanical Subcontractor, Vendor | Mechanically Complete GT |
C46 | Steam Turbine Mechanical Completion | 8 | C20, C30, C39 | Mechanical Subcontractor, Vendor | Mechanically Complete ST |
C47 | HRSG Mechanical Completion | 6 | C21, C30, C39 | Mechanical Subcontractor, Vendor | Mechanically Complete HRSG |
C48 | Balance of Plant Mechanical Completion | 10 | C25, C26, C27, C28, C29, C31, C39 | Mechanical Subcontractor | Mechanically Complete BOP |
C49 | Electrical System Completion | 8 | C34, C35, C36, C37, C38, C41, C42, C43, C44 | Electrical Subcontractor | Completed Electrical Systems |
C50 | Control System Completion | 6 | C40, C49 | Control System Vendor | Completed Control System |
C51 | Instrument Loop Checks | 8 | C39, C49, C50 | Instrumentation Subcontractor | Completed Loop Checks |
C52 | Motor Rotation Checks | 4 | C49 | Electrical Subcontractor | Completed Rotation Checks |
C53 | Hydrostatic Testing | 6 | C30, C31 | Piping Subcontractor, QA/QC Team | Hydrostatic Test Reports |
C54 | Pipe Flushing and Cleaning | 8 | C53 | Piping Subcontractor | Pipe Cleaning Reports |
C55 | Insulation Completion | 10 | C32, C54 | Insulation Subcontractor | Completed Insulation |
C56 | Painting and Coating | 12 | C45, C46, C47, C48 | Painting Subcontractor | Completed Painting |
C57 | Punch List Development | 4 | C55, C56 | Construction Manager, QA/QC Team | Punch List |
C58 | Punch List Resolution | 8 | C57 | All Subcontractors | Resolved Punch List Items |
C59 | Construction Completion Documentation | 6 | C58 | Construction Manager, Document Control | Construction Completion Dossier |
C60 | Systems Turnover to Commissioning | 4 | C59 | Construction Manager, Commissioning Manager | System Turnover Packages |
Milestone ID | Description | Schedule Date (weeks from construction start) |
---|---|---|
CM1 | Construction Mobilization Complete | Week 4 |
CM2 | Site Preparation Complete | Week 14 |
CM3 | Major Foundations Complete | Week 26 |
CM4 | Buildings Enclosed | Week 46 |
CM5 | Gas Turbine Set on Foundation | Week 52 |
CM6 | Steam Turbine Set on Foundation | Week 52 |
CM7 | HRSG Erection Complete | Week 58 |
CM8 | Main Piping Systems Complete | Week 78 |
CM9 | Electrical Systems Complete | Week 86 |
CM10 | Control Systems Complete | Week 92 |
CM11 | Mechanical Completion of All Systems | Week 96 |
CM12 | Construction Substantial Completion | Week 110 |
CM13 | Systems Turnover to Commissioning Complete | Week 120 |
-
Site Preparation and Civil Works
- Site clearing and grading
- Gas turbine and steam turbine foundations
- Turbine building construction
-
Major Equipment Installation
- Gas turbine delivery and setting
- Steam turbine delivery and setting
- HRSG erection
-
Piping Systems
- Main piping installation
- Hydrostatic testing
- Pipe flushing and cleaning
-
Electrical and Control Systems
- Cable installation
- Control system installation
- Instrument loop checks
-
Completion Activities
- Mechanical completion
- Punch list resolution
- Systems turnover
-
Safety Management
- Daily toolbox meetings
- Weekly safety inspections
- Monthly safety audits
- Safety training programs
- Permit-to-work system implementation
-
Quality Control Inspections
- Foundation inspections
- Structural steel inspections
- Welding inspections
- Electrical installation inspections
- Instrument installation inspections
-
Testing and Verification
- Concrete strength testing
- Welding non-destructive testing
- Pressure testing of piping
- Electrical continuity and insulation testing
- Instrument calibration verification
-
Documentation Control
- As-built drawing development
- Material certification verification
- Test report documentation
- Non-conformance reporting and resolution
- Vendor documentation management
-
Interface with Engineering
- Design clarification requests
- Field change requests
- As-built documentation
- Technical query resolution
-
Interface with Procurement
- Material receiving and inspection
- Storage and preservation
- Vendor technical support coordination
- Material shortage resolution
-
Interface with Commissioning
- System turnover planning
- Pre-commissioning activity coordination
- Commissioning support
- Punch list management
-
Interface with Operations
- Operator training during construction
- Operations input on accessibility
- Spare parts management
- Operating manual development support
-
Labor Resources
- Civil workers: 100-150 at peak
- Mechanical workers: 150-200 at peak
- Electrical workers: 100-150 at peak
- Instrumentation technicians: 50-75 at peak
- Support staff: 30-50 throughout
-
Major Construction Equipment
- Tower cranes: 2-3
- Mobile cranes: 4-6
- Excavators and bulldozers: 6-8
- Concrete batch plant: 1
- Welding machines: 50-75
- Scaffolding: Extensive throughout site
-
Temporary Facilities
- Construction offices
- Material laydown areas
- Fabrication shops
- Worker facilities
- Temporary power and utilities
This construction phase schedule provides a comprehensive framework for managing the physical build-out of a combined cycle power plant, ensuring all activities are properly sequenced, resourced, and controlled to achieve mechanical completion and readiness for commissioning.